Project Introduction
Construction of an integrated photovoltaic-storage-charging power plant system.
Adopt energy management system (EMS) for coordinated control and energy optimization management of light-storage-charging equipments.
Using Dyness industrial and commercial energy storage products, such as DH200F, with remote OTA function, to realize product optimization and upgrade remotely, and to reduce the user's operation cost.
The planned construction scale of the photovoltaic system is 18kW, the planned construction capacity of the energy storage system is 100kW/215kWh, and the super charging pile is 640kW.
The photovoltaic-storage system is DC-coupled through DC/DC modules and connected to the AC bus of the distribution network after the energy storage PCS.
Project benefits
Realization of peak and valley arbitrage to help users obtain electricity bill saving benefits;
Dynamic capacity increase reduces the impact of supercharging equipment operation on the power grid and reduces the cost of transformer upgrades;
Packaged with charging pile assets as a “flexible load”, participating in demand-side response together, and supporting the V2G operation mode of charging piles by colleagues to obtain more revenue.